PTS Data Center Solutions Project Process
Over many years PTS has developed a proven project process to plan, design, and build data centers, computer rooms, and server rooms. The process includes comprehensive array of services geared to design, build, commission, monitor, manage, operate, and maintain mission critical facilities, such data centers, computer rooms, server rooms, and network operations centers. Through experience we have developed this Data Center Facility Project Process which allows us to repeatedly deliver within schedule, scope, and budget.
PTS' eleven step progression of the data center project process is shown in the following diagram:
Typically, the initial four project phases are bundled as
Planning & Feasibility. This allows PTS to project the true requirements for new data center design and re-design of existing facilities. Key Design Criteria, or "Needs", includes establishing load, availability, and deployment density design criteria.
From there, PTS performs a comprehensive Site Survey to establish existing conditions and facility constraints. For a new space this survey includes looking for sources of power, communications lines and possibly chilled water as well as locations for landing generators, switchgear, UPS and heat rejection equipment.
After completing the Needs and Survey, PTS establishes recommendations for upgrades or improvements. We then develop plans and visual representations of our concepts in the Plan stage. Plans usually include
CFD modeling, one-lines, drawings, project cost estimating, and master scheduling. At the conclusion of the planning phase, clients have a true understanding of the project scope, schedule, and budget.
From here, clients can leverage
PTS Design & Engineering Services for mechanical, electrical, structured cabling, IT, and other areas of the full data center project process. After design is completed and accepted by the client PTS provides Procurement Services, Data Center Project Management, Construction Management, Contractor Management, Commissioning for facility related supporting infrastructure, and Implementation Services for IT related infrastructure.
To learn more about PTS' Data Center Project
Process to support your data center, computer room, server room or
other mission critical build-out,
contact PTS
or visit: